ITP — INSPECTION TEST PLAN

ITP No: 5014  |  Concrete Works  |  AS 3600 / AS 3610
Project Details
Inspection & Test Plan — Concrete Works
Inspection / Test Point
Work Activity
Timing /
Frequency
Inspection /
Verification /
Test Done By
Acceptance
Criteria
References
(Procedure, Specs,
Dwgs, Standards)
Comments /
Record Type
Sign-off
Complete
Person's
Name
NCR
#
1. PRE-CONSTRUCTION — DOCUMENTATION & COMPLIANCE
Reinforcement inspection
Ensure reinforcing installed per engineer's design
Prior to pour Structural Engineer's Certificate
Current Documentation
Check latest revisions — ensure all design drawings, specifications & procedures are current
Progressive Qualified Structural Engineer design Drawing No:
Drawing No:
Drawing No:
Site Risk Assessment
Assess all risks — gas location, power lines, etc.
Prior to start Documented in site safety file
Site Induction
General construction induction card required. All personnel inducted prior to commencing.
Prior to start White card verified. Site induction register signed.
SWMS
All personnel have contributed to, read and signed relevant SWMS prior to commencing works
Prior to start SWMS signed by all workers SWMS Ref:
2. SITE ESTABLISHMENT
Site boundary & fencing
Temporary security fence & access gate erected. Boundary fence & shade cloth installed.
Initial set-up As per DA, Site Plans & Specifications
Site Access
Check site access — any restrictions to be written in site safety rules / traffic management plan
Prior to start Discussed during site induction
Survey / Set-out
Check set-out and bulk earthworks levels
Progressive As per current design dwgs
3. UNDERGROUND SERVICES
Dial Before You Dig records on site Prior to start DBYD records obtained
Services Locator undertaken and identified Prior to start All services located & marked
Locate all existing services in/above ground — ensure none within excavation area Prior to start Services clear of excavation zone
4. EROSION & SEDIMENT CONTROL
Erosion & Sediment Control Plan on site and controls in place Prior to earthworks & progressive In accordance with Council DA requirements and approved ESC Plan ESC Plan Ref:
5. EXCAVATION & EARTHWORKS
Check invert level for excavation Progressive WHS Reg Part 6.3 — Excavation Work
Excavation Code of Practice
Stockpile or remove spoil (see ITP Material Waste Classification) Progressive WHS Reg Part 6.3 / Excavation Code
Check spoil for contamination (see ITP Material Waste Classification) Progressive WHS Reg Part 6.3 / Excavation Code
Monitor Earthworks: levels, grade, profile, compaction, stages, noise, dust, safety barriers, lighting, removal of excavated materials, shoring to remaining structures Progressive WHS Reg Part 6.3 / Excavation Code
6. SURFACE PREPARATION — BASE & MEMBRANE
Blind with sand to create smooth surface Prior to underlay Smooth, even surface achieved
Remove hard projections above plane surface Prior to underlay No projections remain
Remove loose material Prior to underlay Surface clean of debris
Wet sand just before laying membrane Prior to underlay Sand dampened
200μm vapour barrier under slabs including integral ground beams. Lap joints 200mm facing away from pour. Seal laps & penetrations with water adhesive tape. Patch/puncture repair. Prior to reo Visual inspection — no punctures, laps correct
7. FORMWORK
Visual / Measure — Class of formwork required (1 to 5) Progressive AS 3610 — Formwork for Concrete Class:
Formwork dimensions, levels & capacity checked Progressive Within specified tolerances
Formwork inspected & signed off by Structural Engineer (for suspended slabs) Progressive Engineer sign-off obtained
Releasing agent / bond breaker applied Prior to reo Product applied per manufacturer spec
8. PILING (if applicable)
Installed in accordance with Piling ITP Prior to reo Piling Company sign-off complete Piling ITP Ref:
Engineer certificate / sign-off complete Prior to reo Certificate provided
Trim top of pile to suit engineer's footing design Prior to reo Trimmed to design level
9. POST-TENSIONING (if applicable)
Installed per Post Tensioning ITP. Inspection by PT Engineer. Prior to pour PT Engineer sign-off
Inspection Certificate provided Prior to pour Certificate on file
Foreman & subbie sign-off — verify all rectification work checked pre-pour Prior to pour Engineer's report verified
10. REINFORCEMENT — PLACEMENT
Steel delivery docket records checked against reo design Progressive Matches design requirements
Fabrication checked as acceptable and matches design Progressive Visual + dimensional check
Loose spoil removed from trench before & after reo placement Progressive Clean trench
Reinforcement placement as per engineer's drawing Progressive Matches structural drawings
Bar chairs in position Progressive Correct type & spacing
Correct cover to reinforcement Progressive As per engineer's specification Cover: mm
Correct laps as specified Progressive Lap length per design Lap: mm
Tie wire bends away from concrete cover Progressive No tie wire within cover zone
Manufacturer's certificates for steel obtained Progressive Mill certs on file
Type, size, splicing & spacing of reinforcement per drawing Progressive Matches structural dwgs
Starter bars — length, size, location/set-out, quantity checked Progressive Correct as per dwgs
11. CONSTRUCTION JOINTS · CORES · EMBEDMENTS · TERMITE
Construction & Control Joints — locations & methods approved Prior to reo Per engineer's design
Holding Down Bolts for structural steel — per Structural Engineer's design Progressive AS 4100 Steel Structures
Penetrations / blackouts — per Structural Engineer's design Progressive Correct size & location
Dowels, keys, fillers & waterstops — type, size, profile & position checked Progressive As per design
Termite Management — penetrations with stainless steel mesh, physical termite barrier installed Progressive AS 3660.1 Termite Management
12. PRE-POUR INSPECTION
Footing checked for loose spoil prior to pour Progressive Clean of debris
Formwork checked — dimensions, levels & capacity Progressive Within tolerances
Cleanliness of forms / membranes Progressive Clean & free of debris
Access to/around pour area — free from trip hazards Progressive Safe access confirmed
Foundation scabbled Progressive Surface prepared
Cover to reo verified Progressive Per specification
Termite treatment verified Progressive Certificate / record
Expansion strips / joints Progressive Correct location & material
Isolation joints Progressive Correct position
Saw cut positions marked Progressive Per engineer's design
Releasing agent / Bond breaker Progressive Applied correctly
Engineer inspection of reinforcement — approval to pour obtained Prior to pour Engineer approval received
13. CONCRETE PLACEMENT — PREPARATION
Placing equipment approved — chutes, pipes, barrow runs secured and supported directly from formwork Progressive Equipment safe & adequate
Pumping equipment for type and capacity Progressive Correct pump for job
Free fall within specified limits to avoid segregation Progressive Max 1.5m free fall
Point of discharge as close as possible to final position Progressive Discharge point optimal
Vibrators — number and type adequate Progressive Sufficient vibrators
Power floats available Progressive Equipment ready
Standby equipment (where specified) Progressive Backup available
14. ORDER CONCRETE
Weather Check / Forecast — suitable for pour Progressive Conditions within limits
Concrete specification:
Strength: MPa   Slump: mm
Aggregate Size:   Cement Type:
Admixture:
Delivery notice/arrangements:
Prior to order Concrete 25MPa, slump 80mm per spec Supplier:
Batch plant:
Concrete strength required: MPa   ordered: MPaOrder matches spec
Slump required: mm   ordered: mmOrder matches spec
Concrete test ordered: NATA lab arranged
Dispensing method: Method confirmed
15. CONCRETE PLACEMENT — EXECUTION
Pouring techniques conform — height, vibration, chute, pumpingProgressiveCorrect technique used
Continuity of placement between construction jointsProgressiveContinuous pour maintained
Sequence of pours to minimise shrinkageProgressiveCorrect sequence
Rate of placement to enable correct compactionProgressiveAdequate rate maintained
Correct use of mechanical vibratorsProgressiveProper vibration technique
Compaction in horizontal layers as specifiedProgressiveLayers fully compacted
Thoroughly worked between forms and reinforcementProgressiveNo voids
Free from displacement of reinforcement, embedments etc.ProgressiveAll items in position
Concrete vibrated to release entrapped airProgressiveFull compaction
Delivery dockets checked — MPa, slump toleranceProgressiveDockets match order
Max elapsed time from batch plant to discharge:
10–24°C: 2hrs · 24–27°C: 1.5hrs · 27–30°C: 1hr · 30–32°C: 45min
ProgressiveWithin time limits
Top of finished footing level — check for bricks/blocks to suit coursesProgressiveLevel correct
Record: direction of pour, time of delivery, time of pourProgressiveRecorded on pour log
16. CONCRETE FINISHING
Concrete finished to correct levels — Reference Level (RL) & specified finish toleranceDuring & after pourRL achieved · Tolerance: mm
17. CONCRETE TESTING
Slump test — 1 per 50m³ or per structural engineer's requirementsProgressiveStructural Engineer's specsAS 1012.3.1
Slump tests taken — results recordedProgressiveResults: mm
Record direction of pourProgressiveLogged
Cylinders taken for Compressive Strength TestingProgressiveMin 3 per 50m³NATA Lab:
Saw cut design & depth per engineer's designProgressiveSaw cut depth: mm
Design:
18. CONCRETE CURING
Approved Curing Compound
Method: Spray / Water / Air
Product:
ProgressiveChemical composition approved
Curing maintainedProgressiveMin 7 days
Method of application correctProgressivePer manufacturer spec
Application within time specifiedProgressiveWithin window
Protection installedProgressiveProtected from weather/traffic
Strip to engineer's requirementProgressiveFormwork stripped per spec
19. JOINTS — POST POUR
Joint clean & dryProgressiveClean and prepared
Jointing Material ApprovedProgressiveProduct approved
Jointing material neatly flush with adjoining materialsProgressiveNeat finish
Joints subject to water ingress are watertightProgressiveWatertight seal
Concrete face roughened, cleaned, free of loose/soft material, water, foreign matter & laitanceProgressiveSurface prepared
20. CONCRETE COMPRESSIVE TEST RESULTS
Early Compressive Strength daysProgressiveResult: MPa
28-day test results received and checked for compliance28 daysTarget: MPa · Result: MPa
21. FINAL INSPECTION
Completed as per current design documents/drawingsOn completionAll items complete
Position and alignment within tolerancesOn completionWithin tolerance
Free from cracking, spalling and honeycombingOn completionNo defects
Colour consistency and textureOn completionUniform appearance
Free from projections, depressions and grout spillageOn completionSurface clean
Filling of tie bolt recessesOn completionAll filled
Area is clean and tidyOn completionSite clean
W = Witness — Contractor/Engineer/Consultant may inspect, test, review or witness. Work may proceed. H = Hold Point — Work stopped until specified actions completed and passed/approved. S = Surveillance — Monitor status of work & materials on a periodical basis. NC = Non-Conformance — Raised where work item does not comply. 📎 = Verification — Document, drawing, photo, specification, report attached to ITP.
Non-Conformances
DescriptionCorrective Action RequiredResponsible PartyDate to CompleteVerified As Actioned ByDate Closed Out
Sign-Off

Verified by Client (if required)

Company Name:
Print Name:
Position/Title:

Verified by Contractor

Company Name:
Print Name:
Position/Title:

Verified by Other (if required)

Company Name:
Print Name:
Position/Title:
Review, record, document results of inspection, examination or test to ensure results have passed Project Manager:   Contracts Administrator: