| Item | Qty | Unit |
|---|---|---|
| Formwork to slab area (incl. ramp) | 409 | mยฒ |
| Internal band beam edges | 128 | m |
| Slab perimeter edge boards | 94 | m |
| Formwork to columns | 4 | ea |
| Formwork to beam edges (additional) | 4 | ea |
| Formwork to stairs | 1 | LS |
| Steel reinforcement placement | 15 | tonne |
| Concrete placement | 409 | mยฒ |
| Dincel installation (incl. steel + conc) | 328 | mยฒ |
| # | Date | From | Description | Amount | Status |
|---|---|---|---|---|---|
| 1 | Jul 2026 | Khashman Group | First invoice โ full Building 5 works | $16,500 | ๐ Received |
| # | Item | Qty / Spec | Supplier | Status | Delivery |
|---|---|---|---|---|---|
| 01 | Formwork | 409 mยฒ slab + 4 columns | Khashman Group (sub) | ๐จ In progress | On site |
| 02 | Dincel Walls | GF 461 mยฒ + FF 490 mยฒ | Dincel Australia | โณ Ordered | ~7 Aug 2026 |
| 03 | Steel Reinforcement | ~15 tonne (slab + walls) | TBC | โฌ Not ordered | โ |
| 04 | Structural Steel | 16 columns + 643m beams | TBC โ Get quotes โ | โ Not ordered | โ |
| 05 | Windows & Doors | 43 windows + 18 doors | Aluming (AWD0011330) | โ Not ordered | 8โ12 wk lead |
| 06 | External Cladding | ~600 mยฒ (roof + walls) | TBC | โฌ Not ordered | โ |
| 07 | Infill Walls โ Type A | Internal classroom walls | TBC | โฌ Not ordered | โ |
| 08 | Infill Walls โ Type B | Amenities / wet area walls | TBC | โฌ Not ordered | โ |
| 09 | Electrical | Rough-in + fit-off | TBC | โฌ Not ordered | Rough-in stage |
| 10 | Scaffolding | Full perimeter both levels | TBC | โฌ Not ordered | After GF walls |
| Cause | Date | Days | Evidence |
|---|---|---|---|
| Owner-directed Dincel wall relocation Formwork productivity reduced to ~2 personnel |
27 Jul 2026 | ~3 days | Site diary 27 Jul, owner WhatsApp/email, photos |
| Dincel order stopped & re-placed by owner Original delivery 21 Jul โ halted โ re-ordered 30 Jul โ delivery ~7 Aug |
21โ30 Jul 2026 | ~17 days | Original PO, stop-work instruction, re-order 30 Jul |
| Cause | Since | Days | Evidence |
|---|---|---|---|
| Column size width changes โ RESOLVED 3 Aug โ
Primary deck cannot proceed. JAS Engineers โ no ETA |
27 Jul 2026 | โ Resolved 3 Aug | First-issue drawings 27 Jul, RFI, engineer ack |
| Window sizes amended โ order not placed Schedule revised, Aluming quote AWD0011330 invalid. 8โ12 wk lead time |
23 Jun 2026 | TBC | Revised window schedule, owner approval, Aluming quote |
| Document | Count | Status |
|---|---|---|
| ITP Templates | 4 files | โ Templates only โ not yet project-specific |
| SWMS Templates | 30 files | โ Not yet customised for Building 5 |
| JSA Forms | 30 files | โ Templates โ ready for use |
| OH&S Site Management Plan | โ | โ Not started |
| # | Stage | Date | Inspector | Status |
|---|---|---|---|---|
| 1 | Dincel Inspection | TBD | Certifier | โณ Pending |
| 2 | Beam Inspection | TBD | Certifier | โณ Pending |
| 3 | Formwork Installation Inspection | TBD | Certifier | โณ Pending |
| 4 | Suspended Slab Steel Inspection | TBD | Certifier | โณ Pending |
| 5 | Stairs Inspection | TBD | Certifier | โณ Pending |
| 6 | Ramp Inspection | TBD | Certifier | โณ Pending |
| 7 | Structural Steel Inspection | TBD | Certifier | โณ Pending |
| Doc Ref | Type | File | Status |
|---|---|---|---|
| RGP-432 | Subcontract Agreement | RGP-432-Subcontract-Khashman-SIGNED-2026-07-27.pdf | โ Signed 27 Jul |
| CC20260244 | Construction Certificate | CC Plan โ Building 5 โ 15 Cannery Road | โ Issued |
| FP-2026-WGS-B5 | Fee Proposal | FP-2026-WGS-B5-CM-Rev5.pdf | โ Rev 5 |