๐Ÿซ Building 5A & 5B โ€” 15 Cannery Road, Plumpton NSW 2761

R2G-2026-008 ยท Western Grammar School
๐Ÿ—๏ธ Steel Fabricators ๐Ÿ“‹ ITP 5014 โ€” Concrete ๐Ÿ““ Daily Log
Status
โš  AT RISK
2 blockers ยท ~20 days delay
Contractor
AAA Rapid Homes
Principal ยท RGP-432
Subcontractor
Khashman Group
Formwork ยท Signed 27 Jul
Buildings
2
5A + 5B ยท 774 mยฒ GFA
Approval
CC20260244
DA Approved ยท CC Issued

๐Ÿ“‹ Project Information

Client
Western Grammar School ยท Irfan
Site
15 Cannery Road, Plumpton NSW 2761
Project Type
Two-storey education building (commercial)
Approval Pathway
DA โ†’ CC20260244
Contract Type
Rate contract (not fixed-price)
Contractor
AAA Rapid Homes Pty Ltd โ€” Principal Contractor
Subcontractor
Khashman Group Pty Ltd โ€” Formwork ยท RGP-432 ยท Signed 27 Jul 2026
Scope
Full Building 5: Dincel walls, suspended slab, formwork, concreting
Trade Packages
9 (GF Slab โ†’ Performance Stage)
Suppliers
Building Renders
Building 5A & 5B โ€” FrontBuilding 5A & 5B โ€” Courtyard View

๐Ÿ“… Project Timeline

Site Commencement
25 July 2026 โœ…
Engineering Issued
27 July 2026
Dincel Order Paid
30 July 2026
Dincel Delivery
~7 Aug (pending)
Target Completion
Dec 2026 (at risk)
OC Projected
Jan 2027+
Days Elapsed
9 days since commencement
Current Phase
Ground floor walls โ€” blocked
โ›” Primary deck forming BLOCKED โ€” pending column-size engineering amendments from JAS Engineers. No ETA. Critical path suspended.

๐Ÿ“ Scope of Works โ€” Khashman Group (Formwork ยท RGP-432)

ItemQtyUnit
Formwork to slab area (incl. ramp)409mยฒ
Internal band beam edges128m
Slab perimeter edge boards94m
Formwork to columns4ea
Formwork to beam edges (additional)4ea
Formwork to stairs1LS
Steel reinforcement placement15tonne
Concrete placement409mยฒ
Dincel installation (incl. steel + conc)328mยฒ
Quantities only โ€” pricing managed by accounts.

๐Ÿงพ Contractor Invoices

#DateFromDescriptionAmountStatus
1 Jul 2026 Khashman Group First invoice โ€” full Building 5 works $16,500 ๐Ÿ“„ Received
Total Invoiced: $16,500
Paid: $0
Outstanding: $16,500
โš  Dincel size variation not yet costed. Floor plan Rev B requires 110mm โ†’ 155mm wall upgrade. Formal variation with cost + time impact must be raised.

๐Ÿ“ฆ Procurement Register

#ItemQty / SpecSupplierStatusDelivery
01Formwork409 mยฒ slab + 4 columnsKhashman Group (sub)๐Ÿ”จ In progressOn site
02Dincel WallsGF 461 mยฒ + FF 490 mยฒDincel Australiaโณ Ordered~7 Aug 2026
03Steel Reinforcement~15 tonne (slab + walls)TBCโฌœ Not orderedโ€”
04Structural Steel16 columns + 643m beamsTBC โ€” Get quotes โ†’โŒ Not orderedโ€”
05Windows & Doors43 windows + 18 doorsAluming (AWD0011330)โŒ Not ordered8โ€“12 wk lead
06External Cladding~600 mยฒ (roof + walls)TBCโฌœ Not orderedโ€”
07Infill Walls โ€” Type AInternal classroom wallsTBCโฌœ Not orderedโ€”
08Infill Walls โ€” Type BAmenities / wet area wallsTBCโฌœ Not orderedโ€”
09ElectricalRough-in + fit-offTBCโฌœ Not orderedRough-in stage
10ScaffoldingFull perimeter both levelsTBCโฌœ Not orderedAfter GF walls
๐Ÿ“‹ Legend: ๐Ÿ”จ In progress ยท โณ Ordered/Awaiting ยท โฌœ Not started ยท โŒ Overdue/Blocked

โ›” Critical Path Blockers

โœ… Beam setup โ†’ โ›” Primary deck
BLOCKED: column sizes
โ†’ โณ Slab โ†’ โณ Lock-up
Immediate blockers:
1. Engineering amendments (column sizes) โ€” JAS Engineers, no ETA
1. Dincel delivery โ€” expected ~7 Aug (8-day manufacturing from 30 Jul)
2. Window order โ€” sizes not locked, can't place order (8โ€“12 wk lead time)

โฑ๏ธ Extensions of Time โ€” Delay Register

โœ… Confirmed โ€” ~20 days

CauseDateDaysEvidence
Owner-directed Dincel wall relocation
Formwork productivity reduced to ~2 personnel
27 Jul 2026 ~3 days Site diary 27 Jul, owner WhatsApp/email, photos
Dincel order stopped & re-placed by owner
Original delivery 21 Jul โ†’ halted โ†’ re-ordered 30 Jul โ†’ delivery ~7 Aug
21โ€“30 Jul 2026 ~17 days Original PO, stop-work instruction, re-order 30 Jul

โ›” Unresolved โ€” Duration Unknown

CauseSinceDaysEvidence
Column size width changes โ€” RESOLVED 3 Aug โœ…
Primary deck cannot proceed. JAS Engineers โ€” no ETA
27 Jul 2026 โœ… Resolved 3 Aug First-issue drawings 27 Jul, RFI, engineer ack
Window sizes amended โ€” order not placed
Schedule revised, Aluming quote AWD0011330 invalid. 8โ€“12 wk lead time
23 Jun 2026 TBC Revised window schedule, owner approval, Aluming quote
โš  EOT not submission-ready. Every delay row above lacks backing document references. Owner instructions, purchase orders, engineer correspondence, and site photos must be attached before a formal EOT claim can be submitted. Pattern: owner design indecision (2 changes in 4-day window) โ€” systemic risk of further mid-build changes.

๐Ÿฆบ HSEQ โ€” ITP / SWMS / OH&S

DocumentCountStatus
ITP Templates4 filesโš  Templates only โ€” not yet project-specific
SWMS Templates30 filesโ›” Not yet customised for Building 5
JSA Forms30 filesโš  Templates โ€” ready for use
OH&S Site Management Planโ€”โ›” Not started
โœ… All templates copied to project. Web-fillable ITP 5014 ready:
๐Ÿ“‹ Open ITP 5014 โ€” Concrete Works
ITPs/ (4 .doc) ยท SWMS Forms/ (30 .docx) ยท JSA Forms/ (30 .docx) ยท Contract-Tekton-Formworks-RGP-425.pdf
โ›” Project-specific SWMS are overdue. Templates exist but must be customised with R2G-2026-008 project details, AAA Rapid Homes contractor info and Khashman Group formwork subcontractor, and Building 5 site-specific hazards. High-risk formwork and concreting SWMS are legally required before work proceeds.

๐Ÿ” Critical Stage Inspections (CC20260244)

#StageDateInspectorStatus
1Dincel InspectionTBDCertifierโณ Pending
2Beam InspectionTBDCertifierโณ Pending
3Formwork Installation InspectionTBDCertifierโณ Pending
4Suspended Slab Steel InspectionTBDCertifierโณ Pending
5Stairs InspectionTBDCertifierโณ Pending
6Ramp InspectionTBDCertifierโณ Pending
7Structural Steel InspectionTBDCertifierโณ Pending

๐Ÿ“ Project Documents

Doc RefTypeFileStatus
RGP-432Subcontract AgreementRGP-432-Subcontract-Khashman-SIGNED-2026-07-27.pdfโœ… Signed 27 Jul
CC20260244Construction CertificateCC Plan โ€” Building 5 โ€” 15 Cannery Roadโœ… Issued
FP-2026-WGS-B5Fee ProposalFP-2026-WGS-B5-CM-Rev5.pdfโœ… Rev 5

๐Ÿ“‹ Project Daily Progress Report

Loading...
๐Ÿ“ Updated daily

๐Ÿ“Œ Project Summary

Current Phase
Blocked
Column engineering pending
Financial
$131,835 est.
$16,500 invoiced ยท $0 paid
Key Actions
5 items
Chase engineer ยท Pay invoice ยท SWMS ยท EOT evidence
๐Ÿ”ด Chase JAS Engineers โ€” column size amendments (no ETA, critical path blocked)
๐Ÿ”ด Complete SWMS โ€” formwork, concreting, structural steel (legally overdue)
๐Ÿ”ด Gather EOT evidence โ€” owner instructions, POs, engineer correspondence, site photos
๐ŸŸ  Pay Khashman Group invoice #1 โ€” $16,500 (Formwork)
๐ŸŸ  Raise Dincel size variation (110mmโ†’155mm) โ€” cost + time impact
๐ŸŸ  Lock window sizes โ†’ place order (8โ€“12 week lead time)
๐ŸŸ  Customise ITP templates from NAS for project-specific use
๐ŸŸข Contract signed ยท CC issued ยท Site commenced