๐Ÿซ Building 5A & 5B โ€” 15 Cannery Road, Plumpton NSW 2761

R2G-2026-008 ยท Western Grammar School
๐Ÿ—๏ธ Steel Fabricators ๐Ÿ“‹ ITP 5014 โ€” Concrete ๐Ÿ““ Daily Log
Status
โš  AT RISK
2 blockers ยท ~20 days delay
Contractor
AAA Rapid Homes
Principal ยท RGP-432
Subcontractor
Khashman Group
Formwork ยท Signed 27 Jul
Buildings
2
5A + 5B ยท 774 mยฒ GFA
Approval
CC20260244
DA Approved ยท CC Issued

๐Ÿ“‹ Project Information

Client
Western Grammar School ยท Irfan
Site
15 Cannery Road, Plumpton NSW 2761
Project Type
Two-storey education building (commercial)
Approval Pathway
DA โ†’ CC20260244
Contract Type
Rate contract (not fixed-price)
Contractor
AAA Rapid Homes Pty Ltd โ€” Principal Contractor
Subcontractor
Khashman Group Pty Ltd โ€” Formwork ยท RGP-432 ยท Signed 27 Jul 2026
Scope
Full Building 5: Dincel walls, suspended slab, formwork, concreting
Trade Packages
9 (GF Slab โ†’ Performance Stage)
Suppliers
Building Render
Building 5A & 5B Render

๐Ÿ“… Project Timeline

Site Commencement
25 July 2026 โœ…
Engineering Issued
27 July 2026
Dincel Order Paid
30 July 2026
Dincel Delivery
~7 Aug (pending)
Target Completion
Dec 2026 (at risk)
OC Projected
Jan 2027+
Days Elapsed
9 days since commencement
Current Phase
Ground floor walls โ€” blocked
โ›” Primary deck forming BLOCKED โ€” pending column-size engineering amendments from A.L. Wood Engineers. No ETA. Critical path suspended.

๐Ÿ’ฐ Subcontract Rates โ€” Khashman Group (Formwork ยท RGP-432)

ItemQtyUnitRateTotal
Formwork to slab area (incl. ramp)409mยฒ$130$53,170
Internal band beam edges128m$40$5,120
Slab perimeter edge boards94m$30$2,820
Formwork to columns4ea$900$3,600
Formwork to stairs1LS$6,000$6,000
Steel reinforcement placement15tonne$1,200$18,000
Concrete placement409mยฒ$20$8,180
Dincel installation (incl. steel + conc)328mยฒ$70$22,960
Estimated Subtotal (ex GST)$119,850
GST (10%)$11,985
Estimated Total (inc GST)$131,835
Rate contract โ€” measured quantities. Steel & concrete supplied by AAA Rapid Homes Pty Ltd.

๐Ÿงพ Contractor Invoices

#DateFromDescriptionAmountStatus
1 Jul 2026 Khashman Group First invoice โ€” full Building 5 works $16,500 ๐Ÿ“„ Received
Total Invoiced: $16,500
Paid: $0
Outstanding: $16,500
โš  Dincel size variation not yet costed. Floor plan Rev B requires 110mm โ†’ 155mm wall upgrade. Formal variation with cost + time impact must be raised.

๐Ÿ“ฆ Procurement Register

#ItemQty / SpecSupplierStatusDelivery
01Formwork409 mยฒ slab + 4 columnsKhashman Group (sub)๐Ÿ”จ In progressOn site
02Dincel WallsGF 461 mยฒ + FF 490 mยฒDincel Australiaโณ Ordered~7 Aug 2026
03Steel Reinforcement~15 tonne (slab + walls)TBCโฌœ Not orderedโ€”
04Structural Steel16 columns + 643m beamsTBC โ€” Get quotes โ†’โŒ Not orderedโ€”
05Windows & Doors43 windows + 18 doorsAluming (AWD0011330)โŒ Not ordered8โ€“12 wk lead
06External Cladding~600 mยฒ (roof + walls)TBCโฌœ Not orderedโ€”
07Infill Walls โ€” Type AInternal classroom wallsTBCโฌœ Not orderedโ€”
08Infill Walls โ€” Type BAmenities / wet area wallsTBCโฌœ Not orderedโ€”
09ElectricalRough-in + fit-offTBCโฌœ Not orderedRough-in stage
10ScaffoldingFull perimeter both levelsTBCโฌœ Not orderedAfter GF walls
๐Ÿ“‹ Legend: ๐Ÿ”จ In progress ยท โณ Ordered/Awaiting ยท โฌœ Not started ยท โŒ Overdue/Blocked

โ›” Critical Path Blockers

โœ… Beam setup โ†’ โ›” Primary deck
BLOCKED: column sizes
โ†’ โณ Slab โ†’ โณ Lock-up
Immediate blockers:
1. Engineering amendments (column sizes) โ€” A.L. Wood Engineers, no ETA
2. Dincel delivery โ€” expected ~7 Aug (8-day manufacturing from 30 Jul)
3. Window order โ€” sizes not locked, can't place order (8โ€“12 wk lead time)

โฑ๏ธ Extensions of Time โ€” Delay Register

โœ… Confirmed โ€” ~20 days

CauseDateDaysEvidence
Owner-directed Dincel wall relocation
Formwork productivity reduced to ~2 personnel
27 Jul 2026 ~3 days Site diary 27 Jul, owner WhatsApp/email, photos
Dincel order stopped & re-placed by owner
Original delivery 21 Jul โ†’ halted โ†’ re-ordered 30 Jul โ†’ delivery ~7 Aug
21โ€“30 Jul 2026 ~17 days Original PO, stop-work instruction, re-order 30 Jul

โ›” Unresolved โ€” Duration Unknown

CauseSinceDaysEvidence
Column size width changes โ€” engineering amendments
Primary deck cannot proceed. A.L. Wood Engineers โ€” no ETA
27 Jul 2026 TBC First-issue drawings 27 Jul, RFI, engineer ack
Window sizes amended โ€” order not placed
Schedule revised, Aluming quote AWD0011330 invalid. 8โ€“12 wk lead time
23 Jun 2026 TBC Revised window schedule, owner approval, Aluming quote
โš  EOT not submission-ready. Every delay row above lacks backing document references. Owner instructions, purchase orders, engineer correspondence, and site photos must be attached before a formal EOT claim can be submitted. Pattern: owner design indecision (2 changes in 4-day window) โ€” systemic risk of further mid-build changes.

๐Ÿฆบ HSEQ โ€” ITP / SWMS / OH&S

DocumentCountStatus
ITP Templates4 filesโš  Templates only โ€” not yet project-specific
SWMS Templates30 filesโ›” Not yet customised for Building 5
JSA Forms30 filesโš  Templates โ€” ready for use
OH&S Site Management Planโ€”โ›” Not started
โœ… All templates copied to project. Web-fillable ITP 5014 ready:
๐Ÿ“‹ Open ITP 5014 โ€” Concrete Works
ITPs/ (4 .doc) ยท SWMS Forms/ (30 .docx) ยท JSA Forms/ (30 .docx) ยท Contract-Tekton-Formworks-RGP-425.pdf
โ›” Project-specific SWMS are overdue. Templates exist but must be customised with R2G-2026-008 project details, AAA Rapid Homes contractor info and Khashman Group formwork subcontractor, and Building 5 site-specific hazards. High-risk formwork and concreting SWMS are legally required before work proceeds.

๐Ÿ” Critical Stage Inspections (CC20260244)

StageDateInspectorStatus
1. Piering / FootingsExisting (GF slab)Certifierโœ… Complete (prior phase)
2. Slab ReinforcementTBDCertifierโณ Pending
3. Frame / StructuralTBDCertifierโณ Pending
4. Wet Area WaterproofingTBDCertifierโณ Pending
5. Stormwater DrainageTBDCertifierโณ Pending
6. Final / OCJan 2027+Certifierโณ Future

๐Ÿ“ Project Documents

Doc RefTypeFileStatus
RGP-432Subcontract AgreementRGP-432-Subcontract-Khashman-SIGNED-2026-07-27.pdfโœ… Signed 27 Jul
CC20260244Construction CertificateCC Plan โ€” Building 5 โ€” 15 Cannery Roadโœ… Issued
FP-2026-WGS-B5Fee ProposalFP-2026-WGS-B5-CM-Rev5.pdfโœ… Rev 5

๐Ÿ“‹ Project Daily Progress Report

Loading...
๐Ÿ“ Updated via Hermes Agent or email rex@r2gprojects.com

๐Ÿ“Œ Project Summary

Current Phase
Blocked
Column engineering pending
Financial
$131,835 est.
$16,500 invoiced ยท $0 paid
Key Actions
5 items
Chase engineer ยท Pay invoice ยท SWMS ยท EOT evidence
๐Ÿ”ด Chase A.L. Wood Engineers โ€” column size amendments (no ETA, critical path blocked)
๐Ÿ”ด Complete SWMS โ€” formwork, concreting, structural steel (legally overdue)
๐Ÿ”ด Gather EOT evidence โ€” owner instructions, POs, engineer correspondence, site photos
๐ŸŸ  Pay Khashman Group invoice #1 โ€” $16,500 (Formwork)
๐ŸŸ  Raise Dincel size variation (110mmโ†’155mm) โ€” cost + time impact
๐ŸŸ  Lock window sizes โ†’ place order (8โ€“12 week lead time)
๐ŸŸ  Customise ITP templates from NAS for project-specific use
๐ŸŸข Contract signed ยท CC issued ยท Site commenced
R2G-2026-008 ยท Building 5A & 5B ยท 15 Cannery Road Plumpton ยท Western Grammar School ยท Updated 3 Aug 2026