Beam 1.7 site discrepancy — engineer to support both sides of wall
Site discrepancy identified due to lack of engineering details for beam size 1.7 (constructed above basement staircase). Engineer (JAS) to support beam on both sides of the wall. Discussed new column locations with Irfan — confirmed. Discussed new beams not part of original scope — identified and clarified with Irfan. Job is correct, no major changes required or any errors at this point.
— R2G / Sinan + JAS Engineers
2026-08-18 site_walk
Site walk with client — beams, columns, staircase location confirmed
Site walk with Irfan (client Irfan) on 18 Aug 2026. Identified location of all beams, columns, staircase and other important details. Window 1 (classroom 4) to be reduced in size to provide more storage space. Staircase orientation identified — requires relocation of one existing column to suit the change.
— R2G / Sinan + Irfan
2026-08-16 engineering
All engineering details completed and received
Final structural engineering package received from JAS Engineers: full slab + beams design, all structural details, revised plan (with staircase/slab landing/hall wall changes) finalised. All engineering deliverables complete — JAS Invoice 15CRP15 ($18,672.50) accompanies this delivery. Ready for procurement and construction.
— JAS Engineers (Jamal) / Sinan
2026-08-13 design
Revised plan issued — staircase orientation, slab landing, hall wall changes
Revised floor plan issued (13 Aug) with further changes: staircase orientation adjusted, suspended slab landing extended for stairs, hall wall location changed. Requires JAS Engineers re-check on structural implications (stair reinforcement + landing load path). Coordinate with Star Reo pricing — possible re-design impact on bent-bar balance (9.6t N16).
— Sinan (R2G)
2026-08-12 engineering
Column relocation request — stairs alignment
Sinan requested column relocation to align with stairs. Basement beam locations grey-marked on plan. Awaiting JAS confirmation.
— Sinan (R2G)
2026-08-12 engineering
Final structural drawings + Tax Invoice received
JAS Engineers reissued 11-page structural set with reinforced steel details (JS202125/ST Final). Tax Invoice 15CRP15 ($18,672.50) attached — URGENT payment pending. BSB 06 2133 / Acc 10576880.
— JAS Engineers
2026-08-10 engineering
Jamal — slab + beams design commitment
Jamal (JAS Engineers) via WhatsApp: 'i will send you tonight or tomorrow the slabs, and beams design.' Awaiting delivery. Bent-bar balance (9,590 kg N16) on hold pending.
— JAS Engineers
2026-08-05 design
Window order — new plan sent to team
Window sizes confirmed. Revised plan sent to team today for review. Order to be placed after confirmation.
— Owner / R2G
2026-07-27 engineering
Engineering drawings issued
First-issue structural drawings from JAS Engineers. Column sizes require amendment — RFI raised.
— JAS Engineers
2026-06-23 design
Window schedule revised
Window sizes amended. Existing Aluming quote AWD0011330 invalidated. New quote outstanding. 8-12 week lead time once ordered.