Action Items
R2G-2026-008 โ 15 Cannery Road, Plumpton NSW 2761 โ Last updated 2 September 2026
Variations in Draft โ Not Action Items
These are variations being tracked but not yet ready for action. More items will be added as they arise.
3 columns over contracted 4 at $900/each = $2,700 ex GST / $2,970 inc. Already reflected in KG-2026-003 issued 1 Sep 2026. Formal paperwork to be issued at a later date when more items are added to the VO. Currently in draft only โ no action required.
Cedar Steel itemised split quote (fabrication vs installation)
Tonia Chaiban to provide itemised split so WGS can compare full S&I vs supply-only. Phone chase needed โ email not sufficient at this stage. Quote CQ085802 ($94,500 ex / $103,950 inc) expires Friday 4 Sep.
Crane booking for steel lift to deck
Once steel delivery date is confirmed (Thu/Fri this week), book crane for the same day. Steel beams are too large and heavy for manual handling per site contractor.
Follow up Build a Steel final quote + installer intros
Build a Steel finalising their prices โ get written quote. Requested Cedar/Build a Steel installer intros โ chased today, follow up tomorrow. Need pricing in writing before Friday.
JAS engineering finalisation (side extension + bathroom section + bracing details)
Followed up with Jamal (JAS Engineers). At his office today to clarify reinforcement layout discrepancies. Once finalised, Star Reo can start manufacturing. Target delivery end of Thu 3 / early Fri 4 Sep.
Roofing โ get written quotes from 2 roofers contacted today
Followed up with 2 roofers today. Need written quotations and decision by end of week so roofing can be finalised alongside lock-up target (30 Sep).
Khashman KG-2026-003 payment follow-up
Invoice issued 1 Sep 2026: $13,442 inc GST (net $13,038.74 after 3% retention). 7-day terms โ due 8 Sep 2026. Chase AAA Rapid Homes if not received by end of week.
JAS final invoice 15CRP15 ($18,672.50) โ URGENT payment chase
Final structural drawings delivered 12 Aug. Tax invoice outstanding for 22 days. Pay BSB 06 2133 / Acc 10576880. Critical โ blocks relationship with structural engineer.
Aluming Windows & Doors โ decide and place order
Quote AWD0011330 received. 8โ12 week lead time. Decision needed to keep on critical path for lock-up (30 Sep target). Compare with China quote option per P&D meeting item #5.
External cladding โ discuss with Peter (CTM to evaluate)
From P&D meeting item #6. Subject to JAS calculation (now in progress). Options to evaluate. Discuss with Peter for next steps.
Internal cladding โ acoustic + Jig Rock evaluation
From P&D meeting item #7. Evaluate options from acoustic perspective. Humayoon + Huzaifa to lead.
Ceiling structure design โ Sinan
From P&D meeting item #8. Design + panel sizes + light cage protection for lights. Defer until steel lock-up is complete.
Concrete pour complete โ 49 mยณ across 7 columns + Dincel walls
Saturday 29 Aug 2026. 98.5% job fill. Site cleared to move into next stage: steel fixing for suspended slab and beams. Triggers Khashman RGP-432 Payment 3 milestone.
Khashman KG-2026-003 invoice issued
Dincel work completed (256 mยฒ ร $70 = $17,920 ex, less $12,000 paid in KG-2026-002 = net $5,920) + concrete columns (7 ร $900 = $6,300). Net subtotal $12,220 ex GST + GST $1,222 = $13,442 inc. Less 3% retention ($403.26) = $13,038.74 net payable. Due 8 Sep 2026.
Khashman KG-2026-002 marked paid (25 Aug 2026)
$29,700 inc GST progress payment โ Formwork + Dincel installation. Cleared 11 days after 7-day terms deadline. Now $0 outstanding on this invoice.
Star Reo reinforcement steel invoice processed
Invoice raised by Star Reo for reinforcement steel order. Formally processed by R2G accounts in-house + forwarded to builder (AAA Rapid Homes).
Reinforcement steel discrepancies clarified with JAS
Slight confusion on slab/beam reinforcement layout discrepancies resolved. Went to engineer's office to finalise so steel can start manufacturing. Target delivery Thu 3 / Fri 4 Sep.
Source & Methodology
Items sourced from: P&D Meeting Action Items โ 10 August 2026, Daily Log entries (27 Aug โ 2 Sep 2026), and today's site coordination (Wed 2 Sep 2026). All task checkboxes are interactive โ click to mark done. Section headers are collapsible. State persists in your browser only (localStorage not used to avoid stale state across team members โ treat this as a shared read-only view; updates happen via daily-report.json + regenerate).