R2G-2026-008 — 15 Cannery Road, Plumpton NSW 2761 — Updated 2 Sep 2026
📋 Project: 15 Cannery Road, Plumpton NSW 2761
R2G-2026-008 · Builder: AAA Rapid Homes · Steel scope downstream of Khashman Group RGP-432 formwork & concrete
Scope: Structural steel framing — columns, beams, base plates for two-storey education building
✅ Status (2 Sep 2026): Concrete pour complete (49 m³, 29 Aug). Site cleared to move into next stage — steel fixing for suspended slab and beams. Steel procurement is the active critical path. Steelbuilders (Aro, $39k) and Cedar Steel (Tonia, $103,950) both engaged; EDCON, PSSF, Damo contacted but no formal responses yet.
Active fabricators
Cedar Steel (Bankstown)
Quote in hand — split pending · expires 4 Sep
Steelbuilders Pty Ltd (Glendenning)
Proximate quote received
Outreach — no response
PSSF (Perth Structural Steel Fabricators)
RFQ sent 28 Aug — no acknowledgement
Damo
Direct contact approach 27 Aug
EDCON Steel (Blacktown)
No response since 10 Aug
Builders Steel Direct (BSD)
No response since 8 Aug
Comparison matrix
| Supplier | Distance | Quote status | Price (inc GST) | Lead time | Notes |
|---|---|---|---|---|---|
| Steelbuilders | 5 km | Proximate | $39,000 | 4 weeks | Proximate quote — formal pending. Scope may not include all ancillary items. |
| Cedar Steel | 24 km | Bundle $103,950 · split pending · expires 4 Sep | $103,950 | TBC | Bundle S&I. Split requested 31 Aug. Significantly more expensive — may include scope Steelbuilders doesn't. |
| EDCON Steel | 8 km | No response | — | — | RFQ 10 Aug. No response 23+ days. Recommend close out. |
| PSSF | Perth (interstate) | No acknowledgement | — | — | RFQ 28 Aug. Acknowledgement pending. Long lead time expected (interstate freight). |
| Damo | TBC | Direct approach 27 Aug | — | — | Awaiting response. |
| BSD | 10 km | No response | — | — | RFQ 8 Aug. No response 25+ days. Recommend close out. |
📊 Pricing insight: Steelbuilders' $39k is 62% cheaper than Cedar's $103,950. Three possible reasons: (a) scope gap (Steelbuilders' $39k may not include bracing, base plates, gusset plates); (b) Cedar's price includes installation which Steelbuilders' doesn't; (c) Steelbuilders is over-estimating or under-scoping. Need Steelbuilders formal quote to compare apples-to-apples. Decision required by 4 Sep.
📎 Documents sent with each RFQ:
- Engineering Plan Set v6 (16 pages, JAS Engineers, JS202125/ST Final)
- Building 5 Structural Steel Sheet v6 (1 page, 16 columns + 643m beams)
- Two additional columns noted
- Right-hand steel building adjacent to slab noted
- X-brace both sides noted (per v3 plan)
📞 Required from each fabricator: lead time for quotation → shop drawing → fabrication → delivery to site → installation. Cedar Steel template sent to all.