PD Meeting

P&D Meeting Action Items — Building 5 — 15 Cannery Rd, Plumpton

Date:Monday, 10 August 2026
Project:R2G-2026-008
Attendees:Irfan Afzal, Saiyaz, Huzaifa Rauf, Humayoon Akhter, Sinan Amin

Attachments

P&D Meeting Action Items — Building 5 — 15 Cannery Rd, Plumpton

Meeting Date: 10 August 2026, 1:30 pm – 2:30 pm

Project: R2G-2026-008 — 15 Cannery Road, Plumpton — Irfan (WGS)

Attendees: Irfan Afzal, Saiyaz, Huzaifa Rauf, Humayoon Akhter, Sinan Amin

Prepared by: R2G Projects Pty Ltd


Critical Items — Construction Blockers

1. First Floor Steel Structure Quotes — ACTIVE

Detail Value
Owner Sinan Amin
Suppliers approached Steelbuilders Pty Ltd (J179773), EDCON Steel
Status 🔴 Awaiting responses
Steelbuilders ETA 13–14 August 2026
EDCON Steel No response yet — follow up
Action Sinan to forward in-fill steel drawings, confirm gauge with fabricators

2. Engineering Final Drawings — ACTIVE

Detail Value
Owner JAS Engineers (Jamal Salame, Fady)
Issued 10 August 2026 (draft slab drawing)
Due 11 August 2026 — "by end of tomorrow maximum"
Action Sinan to chase Jamal for finalisation today

3. B5 DA Modification

Detail Value
Owner Sinan Amin
Status "To be launched ASAP" per meeting
Action Lodge via NSW Planning Portal

Procurement — Quote Required This Week

4. Scaffolding (Carpark End — 30m include ramp face)

Detail Value
Owner Huzaifa Rauf + Humayoon Akhter
Issue Local small trans cells run out
Action Compare China quotes vs local availability
Decision Local supplier vs China — within 1 week

5. Doors & Windows

Detail Value
Owner Sinan Amin
Decision "Order within one week if local supplier is cheaper"
Deadline 18 August 2026
Existing BWE Electrical completing marking for fixtures
Action Sinan to decide and place order by 18 Aug

6. External Cladding

Detail Value
Owner Sinan (with Peter) + Huzaifa
Subject to JAS calculation
Options CTM to evaluate
Action Discuss with Peter for options

7. Internal Cladding

Detail Value
Owner Humayoon + Huzaifa
Considerations Acoustic + Jig Rock options
Action Evaluate from acoustic perspective

8. Ceiling Structure

Detail Value
Owner Sinan Amin
Scope Design + panel sizes + light cage protection for lights
Action Sinan to prepare design

Interior Fit-out — Design & Quote Required

# Item Status
9 Indoor sports activities design Not started
10 Sports activity equipment (supply & install) Not started
11 Stage design + AV system drawings Not started
12 Interior lighting signs + LCD displays Not started
13 Mezzanine + storage system design Not started
14 Interior design + decoration Not started
15 Furniture (chairs, tables, staff + VIP chairs) Not started
16 Portable lectern + chair trolleys Not started
17 Storage cupboards Not started
18 Stage curtains + backdrop + lighting Not started
19 Projectors + screens Not started
20 Vinyl tiles (flooring) Not started
21 Non-slip stage + hall decoration items Not started
22 Air conditioning system Not started
23 Curtains + blinds Not started
24 Equipment storage Not started

Sub-Contractors to Engage

# Trade Status
25 Rendering Not engaged
26 Electrical BWE engaged (Loc) for fixture marking
27 Plumbing Not engaged
28 Roofer Not engaged
29 Stage installer Not engaged
30 Audio/Visual (incl. LCD + speakers) Not engaged

Top 5 Immediate Priorities

  1. Steel structure — chase Steelbuilders/EDCON for quotes today
    1. Engineering final drawings — confirm JAS delivery today (was due 11 Aug)
      1. B5 DA Modification — lodge immediately
        1. Doors & windows — decide and order by 18 August 2026
          1. Scaffolding comparison — pull from Huzaifa/Humayoon this week

          2. Notes:

            • Building 5 structure: Steel frame infill with timber framing inside, external steel structure
              • Flooring decision: Vinyl tiles preferred; concrete finish must be smooth and tile-ready
                • Sinan is the primary point of contact for all engineering and procurement follow-ups
                • Prepared: 17 August 2026

                  Next review: 18 August 2026